Wednesday, October 8, 2014

Beams on

Posted on 3:26 PM by cristile
It has been quite some time since we last posted, but we've been very busy on the house. Walls are finally reaching final height and today we decided to muscle up the beams with only three of us and a whole lot of leverage.




We used our 13' pole rafters as a make shift ramp from the bed of the truck to the shortest wall. From there we used a combination of ropes and muscle to shift them up the walls and into place. 



 


Email ThisBlogThis!Share to XShare to Facebook
Posted in | No comments
Newer Post Older Post Home

0 comments:

Post a Comment

Subscribe to: Post Comments (Atom)

Popular Posts

  • First layer of plaster and sub-floor.
    A sample of the final layer of plaster. It will be lighter.  We are putting flag stone down in the bathroom under the clawfoot tub.  The lof...
  • Second set of rafters
    Today we finally reached final wall height and were able to start the second set of rafters for the main house. Each rafter is a 4 diameter ...
  • (no title)
    Thanks Sarah and Lexi for taking these great pictures! 
  • RMH update
    Thought I should post a video of the rocket mass heater (RMH) that will be keeping Katherine and I warm this winter. Many people are skeptic...
  • Roof going up.
  • Kaolin plaster
  • Cobbing the walls
    The cob walls are finally starting to go up. Here you can see the small holes we push into each layer helping bind the next batch of cob to ...
  • Roof edging
    The roof edging was very labor intensive, but totally worth it when finished. All of these boards will serve to hold our living roof from fa...
  • (no title)
  • RMH insulation
    The brickwork heat riser of the RMH is wrapped in hardware cloth and filled with insulation. We decided to use perlite for the insulation an...

Categories

  • Plaster

Blog Archive

  • ▼  2014 (52)
    • ►  December (3)
    • ►  November (5)
    • ▼  October (9)
      • A guide to Earthen Plaster
      • RMH update
      • Roof edging
      • Pond liner on!
      • First plaster
      • No title
      • Roof going up.
      • Second set of rafters
      • Beams on
    • ►  September (4)
    • ►  August (9)
    • ►  July (7)
    • ►  June (10)
    • ►  May (5)
Powered by Blogger.

About Me

cristile
View my complete profile